Lakeway City Park Renovation: What to Expect Before 2027

October 1, 2026

If you've seen the notice on the city's website, you might think Lakeway City Park is about to change. The feedback form on the proposed skate park, bike skills park, and boardwalk trail closed at the end of the day Wednesday, September 30. That reads like a project entering its final stretch. It isn't. According to Community Impact, the timeline the city council approved last November has the earliest public bid for any of this in March 2027, with construction starting that June. The comment period that ended this week was closer to the beginning of a long process than the end of one.

That gap matters if you use the park, and it says something about how Lakeway spends bond money that's worth understanding even if you never touch a skateboard.

What's Actually On The Feedback Form

The plans presented for feedback cover an improved skate park, a new beginner-level bike skills park, a boardwalk trail, overlook platforms, and new pickleball courts. All of it would go into the existing 64-acre City Park on Hurst Creek Road, which already has close to two miles of trails, a Butterfly Garden, a Bark Park, and a kayak launch reachable by water from Hurst Creek Cove.

Engineering firm Dunaway is handling the design work under a $1.02 million contract the city council approved on November 17, 2025. Their proposal includes at least one public meeting for additional resident input beyond the online form, so the September 30 deadline wasn't the last chance to weigh in. Project information is on the city's 2024 Parks Bond page.

Why This Skate Park Needed A Redesign At All

Public comments raised concerns about the difficulty of the existing skate park and area trails.

A Community Impact report says that at a Lakeway City Council meeting on January 16, 2024, a resident named Chase Hop, a professional BMX rider who had lived in Lakeway for three years, told the council that the existing skate park at the Lakeway Swim Center was too advanced for most riders. He said the current setup is difficult to ride even at a professional level, and argued the city needed something built for a wider range of skill.

He wasn't the only one making that case. Mike Girard, president of the Lake Travis Trail Coalition and a former Lake Travis ISD mountain biking coach, told the council that Lakeway's bike trail network is extensive but consistently too advanced for beginners. Members of the Lake Travis ISD mountain bike team, who train on trails throughout the area, backed the push for beginner-friendly terrain alongside the more experienced routes already in place.

The feedback form now includes an improved skate park and a beginner-level bike skills park.

The Biggest Piece Of The Bond Is Also The Slowest

Voters approved the $22 million parks bond in May 2024, and Lakeway City Park's overhaul is the largest single piece of it. At $10.65 million, it's nearly half the entire bond, covering the skate park, bike skills park, boardwalk, overlook platforms, and pickleball courts.

But the biggest line item isn't the one closest to completion. That distinction belongs to a smaller project a few miles away.

Butler Rough Hollow Park, budgeted at roughly $2.1 million and set to include an amphitheater, a mountain bike course, a basketball area, and a multisports field, is further along in a very literal sense. The city council has already approved the purchase of its playground equipment, a $430,738 order from Play & Park Structures. That equipment is sitting in storage, free of charge, waiting for installation sometime in 2026.

So the numbers land like this: the smaller of the two projects already has physical equipment purchased and warehoused for next year. The larger project, the one getting nearly half the total bond, has a signed design contract and a set of engineering drawings still in progress. Nothing has been built. Nothing has even gone out for bid.

That's not a sign anything went wrong. Parks Director Andra Bennett has described the current phase as the final engineering and design work needed after the conceptual plans that got the bond passed in the first place. It's a reminder that "funded" and "built" are two different milestones, and the distance between them can run into years even after voters have already said yes.

Three Years From Yes To Groundbreaking

Laid out on a timeline, the sequence looks like this:

Milestone Date
Voters approve $22M parks bond May 2024
Resident pushback on skate park difficulty January 2024 council meeting
Design services contract with Dunaway approved November 17, 2025
Public feedback window on current design Closed September 30, 2026
Project goes out for bid Expected March 2027
Construction begins Expected June 2027

From the bond vote to the first shovel in the ground is roughly three years. If you're picturing new pickleball courts by next summer, this is the timeline that says otherwise. The version of the park on the drawing board this week won't be walkable until at least 2027, and that's assuming the bid process and construction schedule hold.

While You Wait

The rest of Lakeway's recreation calendar hasn't paused for any of this. On September 26, the city ran a free cornhole tournament next to the Lakeway Swim Center, open to residents on a first-come basis with prizes for the winning teams. On October 4, the Lakeway Arts Committee is hosting a free Masterpiece Concert at the Lakeway Activity Center, featuring Andrew and Sari Pearce along with guest performers.

Separately, the trails behind Lakeway City Hall are currently home to 28 displays set up for Hispanic Heritage Month, running through mid-October and covering the history, culture, and customs of Hispanic communities. It's a different location from the City Park redesign, but it's the same instinct at work: use the public spaces you already have while the bigger projects work through their engineering phase.

None of this replaces what's coming to City Park. But it's a useful reminder that the neighborhood's day-to-day recreation doesn't wait on a construction schedule, even when the biggest single project in a $22 million bond is still months from breaking ground.

For now, residents can follow the design work as it moves toward the bidding stage.