Thomas Ranch's Schedule, Mapped for a Spicewood Home Search

November 19, 2026

Spicewood's biggest change for the next ten years is already on paper. Thomas Ranch is a master-planned community from Areté Collective covering about 2,200 acres between Burnet and Travis counties, with roughly 3,500 homes planned. It stretches from Texas 71 to the banks of the Pedernales River and CR 404. Managing Director Joe Rentfro told DailyTrib that the project could take a decade to finish.

The parts of the plan with published dates are homes, apartments and roads. The downtown, the medical services and a school are planned, but they don't have dates yet. If you're comparing homes in Spicewood this winter, the dated work near an address tells you more about your next few years there than the amenity list in a brochure.

What the counties have approved so far

The approvals have gone from preliminary to final over the past year. On Oct. 28, 2025, the Burnet County Commissioners Court gave preliminary plat approval to 443 lots along CR 404 and Paleface Ranch Road, in unincorporated southeast Burnet County. On May 12, 2026, according to DailyTrib, the county approved final plats for three Thomas Ranch Northwest parcels: 399 lots on 137 acres. On July 14, 2026, it unanimously approved the Thomas Ranch Northwest Phase 3 final plat, 45 lots on a little more than 17 acres.

Most of the land lies elsewhere. About 80 percent of the property is in Travis County. Of the 3,500 planned homes, about 700 will be on the Burnet County side. The Burnet County approvals so far cover only a small part of what's coming.

Rentfro told Community Impact in May 2026 that 1,300 units were in some stage of build-out and that the first residents were expected to move in early in 2027. By the developer's schedule, the first move-ins are only a few months away.

The first wave is a gated club community and a rental complex

Two projects account for most of the 1,300 units Rentfro described.

Nearly 300 of them are in Loraloma, a private golf community inside Thomas Ranch. Its members-only 18-hole course, designed by David McLay Kidd, opened to people who had bought lots there. The developer's status update dates that opening to October 2025 and says Loraloma home construction began in August 2025. Other amenities in Loraloma's plans include a fishing pond, a swimming hole, a recording studio, a dance hall, private dining, a spa and fitness facilities, and Rentfro told Community Impact that "most of these amenities are behind the gate." The Loraloma preferred builder list names Cedar & Oak, Texas Sage, eleV8, Canyon Building, Mattison Reynolds Residential Works and Abode Modern Homes.

Another 500 are apartments at The Oakley, a complex Wasatch Premier Properties is building on a 58-acre site it bought in 2024. Wasatch is also building 100 for-sale townhomes on the same land. In May, its schedule called for construction to start in September 2026, with the first occupancies in late 2027.

The dated part of the plan adds a gated golf community, a large apartment complex and a set of for-sale townhomes. If you're weighing an established acreage property against something newer, those are the homes with move-in dates on the published schedule. Our earlier look at waterfront and acreage living in Spicewood covers the lot-size side of that comparison.

The town-center pieces are planned without dates

The parts of Thomas Ranch that would change daily errands for everyone along Highway 71 are described in the plans without opening dates. Community Impact reports a planned "downtown" of more than 450,000 square feet of retail, dining and office space, including a school and a medical center. The developer's own site uses a smaller number, "250K+" square feet of downtown space.

Rentfro told Community Impact that Baylor Scott & White will provide medical services in the area and is interested in concierge medicine and wellness care, not a traditional emergency room with hospital beds. He also said Thomas Ranch is looking for a school partner for a middle or high school, possibly Marble Falls ISD or a private school. The Thomas Ranch FAQ says the property is currently in Marble Falls ISD. Lake Travis ISD is building Highland Lakes High School nearby, so confirm the district boundary for any specific address.

The plan also lists more than 40 miles of trails, more than 2 miles of Pedernales River frontage and more than 1,200 acres of preserved open space. DailyTrib adds a resort, a dance hall and taphouse, and a sports complex to the long-range list.

Utilities have dates. Thomas Ranch will have its own public water systems drawing from Lake Travis, with 1,603 acre-feet a year under a Lower Colorado River Authority firm water contract. The developer had scheduled its wastewater treatment plant for December 2025, and Community Impact's May 2026 report says the plant was completed in December.

Where the construction sits along Highway 71

Spicewood is a long stretch of highway, so a decade of growth won't feel the same from every driveway. Here is what is scheduled and roughly where, as of the latest dated plans:

Project Location Timing as published
Loraloma Phase 3 roads Hwy. 71 to the north end of Paleface Ranch Road About 18 months of construction once bid; bids were planned for June or July 2026
TxDOT SH 71 Safety Improvement Project, raised median 6.4 miles from Bee Creek Road to Uplands Ridge Drive Scheduled start fall 2025, finish fall 2026
Bee Creek Road improvements Lakehurst Road to Highlands Boulevard Design wrapping up at the end of 2026, completion expected early 2028
Highland Lakes High School and road contract Reimers-Peacock Road off SH 71 $11.88 million road contract awarded March 2025; school opening August 2029
SpiceQ restaurant and retail 5600 Hwy. 71 Construction forecast January 2027 to July 2028

The median project is a safety project. Community Impact describes it as a raised median, not a widening, which changes how turns work along that stretch. If a home you're considering has its driveway or neighborhood entrance between Bee Creek Road and Uplands Ridge Drive, drive the route both ways and check which direction you can actually turn.

SpiceQ is a proposed project of more than 10,000 square feet, valued at $1.8 million in its state filing, according to Community Impact. It's one example of new restaurant and retail interest along the highway that isn't tied to Thomas Ranch's downtown schedule.

Farther east on the corridor, Canyon Ranch Austin at 600 Moonlight Bend is a separate project from Thomas Ranch. Next to it, the Moonlight Bend subdivision received preliminary plat approval in March 2025 for 134 lots. DailyTrib reported that its water and wastewater will come from a newly formed Moonlight Bend MUD. Two new Spicewood communities a few miles apart can have very different utility setups, so ask about utilities early for any new-construction home. Our post on Canyon Ranch's arrival covers how the resort fits into everyday Spicewood dining.

Using the timeline to compare Spicewood homes

First, how close is the home to active construction? A property near CR 404, Paleface Ranch Road or Reimers-Peacock Road will likely sit near road and home building for several years under the published schedules. A property on the eastern end of the corridor near Bee Creek Road is closer to Bee Cave's road work, which is on its own schedule.

Second, are you paying for amenities that exist today? Loraloma's golf course is open to lot owners. The public-facing downtown, the Baylor Scott & White services and any school partnership are still in planning, inside a project Rentfro said could take a decade to finish. A buyer who wants those things should value a home on what's open now and treat the rest as upside.

Third, where will new supply come from? With 500 apartments and 100 townhomes planned at The Oakley and about 3,500 homes across the full plan, much of Spicewood's new housing over the next several years will be new construction inside one master plan. An established home on its own acreage competes with that supply on lot size, mature trees and the fact that it is already finished.

Buyers also have room to ask these questions right now. In October 2026, homes across the Austin metro averaged 76 days on market, sellers received 92.2 percent of their original asking price on average, and inventory stood at 6.2 months, according to the Austin American-Statesman's report on that month's data. Those are metro-wide figures, not Spicewood-specific, but they describe a market where you have time to drive the corridor at rush hour, check the plats near a property and talk with a builder before you write an offer. Our buyer's guide walks through the steps from offer to closing, and our Spicewood neighborhood page covers everyday life along the corridor.

If you're weighing a Spicewood home this winter, 512Vibe Realty Group can help you map a specific address against the Thomas Ranch plats and the Highway 71 road schedule, so you know what's planned near it before you commit. If you already own in Spicewood and wonder how the coming growth might affect your home's value, start with a free home valuation and we'll go through it with you.